Fire safety design review fees are based on the total investment, the applicable fee rate, and any fee reduction policy in effect. For office projects, businesses should first confirm whether the project requires a review and which investment scope is used to calculate the fee.
1. What are fire safety design review fees?
“Fire safety design review fees” is a commonly used term for the government fee charged by a competent state authority to appraise and approve fire prevention and fighting designs. Under Circular 70/2025/TT-BTC, this is a state fee, separate from the cost of consulting, preparing documents, design, construction, or testing fire safety systems.
2. When are fire safety design review fees payable?
Fire safety design appraisal fees apply to projects, buildings, or items that are subject to appraisal and fee collection under applicable regulations. For office projects, consider three cases: new construction, renovation or a change of use, and new construction of an item within a project.
2.1. New construction subject to appraisal
A newly constructed building subject to fire safety design appraisal incurs a fee when the application falls within the cases where fees apply. Before estimating the fee, businesses should confirm whether the building requires appraisal and which authority will conduct it.
The area of a leased office or the scope of an individual interior fit-out is not enough to determine whether a fee is payable. The assessment must be based on the building, item, and scope covered by the fire safety appraisal application.
2.2. Renovation or change of use
For an existing building that is renovated or changes its use, the appraisal fee is calculated based on the total investment for the renovated or repurposed part of the building. The fee base must be limited to the scope covered by the appraisal application; it should not include the value of the entire building or original project.
Renovation or a change of use should be distinguished from a design adjustment. Under the current guidance applied by the Police, design adjustments to a building are not subject to appraisal fees.
2.3. New construction of an item within a project
If a project includes a new item subject to fire safety appraisal, the fee is calculated based on the total investment for that new item within the appraisal scope. The fee base should reflect the value of the item being appraised. Investment in other parts of the project that are not part of the new construction should be excluded.
>> See also: A compilation of fire safety standards in Vietnam: List and regulations
3. Calculating fire safety design review fees
Fire safety design review fees are determined by the investment scale and the type of project or building within the appraisal scope. Businesses should identify the correct investment value to use as the fee base before applying the relevant rate under the regulations.
3.1. Calculation formula
Under Circular 70/2025/TT-BTC, the appraisal fee is calculated using the investment value within the appraisal scope and the rate applicable to each project or building type. The formula is:
Appraisal fee = Total investment used as the fee base × Fee rate
The rates in the fee schedule are expressed as percentages and vary by building type and investment scale. If the fire safety content is appraised by a construction-specialist authority as part of construction investment procedures, the fee is determined under the corresponding regulations on construction project and design appraisal.
3.2. Fee rates by project or building type
The fee rate (%) is determined by the project or building type and its corresponding investment scale. Circular 70/2025/TT-BTC classifies projects and buildings by group and investment scale to establish the applicable rate.
| Project or building type | Up to VND 15 billion | VND 100 billion | VND 500 billion | VND 1,000 billion | VND 5,000 billion | VND 10,000 billion and above |
|---|---|---|---|---|---|---|
| Technical infrastructure and transport | 0.00336% | 0.00182% | 0.00101% | 0.00068% | 0.00038% | 0.00025% |
| Oil and gas, energy, and chemicals | 0.00664% | 0.00359% | 0.00200% | 0.00133% | 0.00074% | 0.00050% |
| Civil and other industrial projects | 0.00484% | 0.00262% | 0.00146% | 0.00097% | 0.00054% | 0.00036% |
| Other projects and buildings | 0.00444% | 0.00240% | 0.00134% | 0.00089% | 0.00050% | 0.00033% |
For an office project, the applicable rate depends on the building type and the project’s legal documents. Once the correct group is identified, compare the total investment with the fee schedule thresholds to determine the rate or calculate an interpolated rate.
3.3. Total investment
Under Circular 70/2025/TT-BTC, the total investment used to calculate the fee is determined in accordance with regulations on construction investment cost management. For renovation, a change of use, or new construction of an item, the fee base is the value of the building or item within the fire safety appraisal scope.
The following costs must be excluded from the fee base:
- Compensation and site clearance costs.
- Support and resettlement costs.
- Land-use costs.
- Value-added tax and other related taxes.
The value used to calculate the fee is before tax. The investor or owner is responsible for the accuracy of the declared total investment and its consistency with the project documents.
If the total investment falls between two thresholds in the fee schedule, the rate is determined by interpolation between the lower and upper thresholds. This method identifies the rate corresponding to the actual investment scale in the application.
Nᵢₜ = Nᵢᵦ − [(Nᵢᵦ − Nᵢₐ) / (Gᵢₐ − Gᵢᵦ)] × (Gᵢₜ − Gᵢᵦ)
| Symbol | Meaning |
|---|---|
| Nᵢₜ | Rate to be determined |
| Gᵢₜ | Total investment to be calculated |
| Gᵢₐ | Upper investment threshold |
| Gᵢᵦ | Lower investment threshold |
| Nᵢₐ | Rate at the upper threshold |
| Nᵢᵦ | Rate at the lower threshold |
The interpolated rate is used to calculate the fee corresponding to the total investment within the appraisal scope.
4. Minimum and maximum fees and fee reduction policies
After calculating the fee based on total investment and the applicable rate, compare it with the minimum and maximum thresholds and any fee reduction policy in effect at the time of payment.
4.1. Regulatory minimum and maximum fees
Under Circular 70/2025/TT-BTC, the fee for a project is subject to the following limits:
- Minimum: VND 500,000 per project.
- Maximum: VND 150,000,000 per project.
These minimum and maximum amounts apply to fees determined under Article 4 of Circular 70/2025/TT-BTC. The amount a business must pay also depends on any fee reduction policy in effect and the notice issued by the collecting authority.
4.2. Time-limited fee reduction policies
Fees during specific periods may be lower than the base amounts under Circular 70/2025/TT-BTC. As of October 7, 2026, distinguish between the following two fee reduction policies:
| Policy | Applicable period | Eligible parties | Applicable rate |
|---|---|---|---|
| Circular 64/2025/TT-BTC | July 1, 2025–December 31, 2026 | Fee payers within the policy’s scope | 50% of the corresponding fee |
| Circular 117/2026/TT-BTC | August 15, 2026–February 28, 2027 | Vietnamese citizens who meet the requirements for Level 2 electronic identification | 50% reduction, with a minimum of VND 250,000 and a maximum of VND 75,000,000 per project |
If a payer qualifies for more than one exemption or reduction under Circular 117/2026/TT-BTC, the highest applicable benefit is used. Benefits cannot be combined to reduce a fee that has already been discounted.
5. Fee calculation example for an office renovation project
The office renovation project falls under the civil and other industrial project category. The total investment within the renovation scope is VND 30 billion. The value used to calculate the fee excludes items that are not part of the fee base and is stated before tax.
Because VND 30 billion falls between the VND 15 billion and VND 100 billion thresholds, the fee rate must be determined by interpolation.
| Data | Value |
|---|---|
| Lower threshold | VND 15 billion |
| Rate at lower threshold | 0.00484% |
| Upper threshold | VND 100 billion |
| Rate at upper threshold | 0.00262% |
| Assumed total investment | VND 30 billion |
Determine the rate:
Nᵢₜ = 0.00484 − [(0.00484 − 0.00262) / (100 − 15)] × (30 − 15) ≈ 0.004448%.
Calculate the base fee:
VND 30,000,000,000 × 0.004448% ≈ VND 1,334,471.
Apply the 50% reduction:
VND 1,334,471 × 50% ≈ VND 667,235.
Check the fee threshold:
The result of VND 667,235 is higher than the minimum applicable in this case, so the estimated amount is approximately VND 667,235.
The actual amount should be checked against the declared total investment, applicable rate, fee reduction policy in effect, and notice from the collecting authority.
6. Preparing and paying fire safety design review fees
For applications handled by the Police, fee payment is tied to the receipt, appraisal, and return of the application. Businesses should confirm the applicable requirements, prepare the fee calculation data, and monitor notices on the Public Service Portal to pay the correct amount.
6.1. Step 1: Confirm that the building is subject to appraisal
The investor should compare the project, building, or item with Appendix III of Decree 105/2025/ND-CP and the provisions amended by Decree 347/2026/ND-CP. The investor should also identify the appraisal authority, as applications handled by the Police and those handled by a construction-specialist authority are subject to different fee arrangements.
6.2. Step 2: Prepare the application
The business prepares the application according to the design type and corresponding appraisal procedure. For technical design or construction drawing applications, the request document, legal documents, and design documents should consistently identify the building scope submitted for appraisal.
In addition to the technical documents, the business should check the total investment used as the fee base. The declared value must match the appraisal scope and follow the fee calculation principles applicable to the project, building, or item.
>> See also: 50+ beautiful and modern office floor plans
6.3. Step 3: Submit the application
The appraisal application can be submitted in person, by post, or online through the Ministry of Public Security Public Service Portal. The business should submit it to the authority with the confirmed jurisdiction to avoid having to transfer or resubmit the application.
6.4. Step 4: The Police receive and appraise the application
The receiving authority checks the application’s contents and validity before carrying out the appraisal:
- Complete and valid application: It is accepted, and a date for returning the result is provided.
- Application requiring completion: The business receives a request for amendments or additional documents before processing continues.
When completing the application, keep the design scope consistent with the declared total investment, as this information directly affects the fee determined after the appraisal result is issued.
6.5. Step 5: Receive the payment notice by email or SMS
For applications subject to fees handled by the Police, the system sends a notice by email or SMS after the appraisal document has been issued. The notice shows the application status and amount payable, and provides information for accessing the application on the Public Service Portal.
6.6. Step 6: Check the fee amount
Before paying, the business should compare the notified amount with the information in the application:
- Total investment used as the fee base.
- Project or building category and applicable rate.
- Minimum and maximum fee limits.
- Fee reduction policy in effect.
If the notified amount does not match the declared information or appraisal scope, the business should seek clarification before paying.
6.7. Step 7: Pay online through the Public Service Portal
After receiving the notice, the business accesses the application on the Ministry of Public Security Public Service Portal and checks the amount payable. The system enables online payment and directs the user to the relevant payment channel to complete the transaction.
6.8. Step 8: Download the receipt and receive the appraisal document
After successful payment, the system records the transaction and allows the user to download the fee receipt from the application details. The business should continue to monitor the application status to receive the result using the registered method: in person, by post, or electronically when supported by the procedure.
The appraisal document may be issued before the system sends the payment notice. Therefore, track the date the appraisal result is issued separately from the date the fee obligation is completed.
7. When fees are notified and payment deadlines
For applications handled by the Police, the payment deadline is based on the notice sent through the system. Businesses should track these dates:
- Fee notice: Issued after the application has been appraised and a payment obligation has arisen.
- Payment deadline: Within 30 days of the system sending the payment notice.
- After the deadline: If payment has not been made within 30 days, the system automatically cancels the application.
Businesses should check the notice as soon as it arrives to allow enough time to verify the amount and complete payment within the required period.
8. Methods for paying fire safety design appraisal fees
For applications handled by the Police, the appraisal fee is paid online through the Ministry of Public Security Public Service Portal using the application details. The business pays after receiving a notice of the amount due.
The payment process may follow these steps:
- Access the application on the Ministry of Public Security Public Service Portal.
- Check the notified fee amount.
- Select online payment and complete the transaction using a method provided by the system.
- Check the payment status and download the receipt from the application details.
Keep the receipt with the project documents as proof of payment and for future reference.
9. Common mistakes that lead to incorrect or additional fees
Errors in fee calculations are often related to total investment, applicable regulations, fee reduction policies, or the authority conducting the appraisal. Businesses should check these factors before budgeting and submitting an application.
9.1. Declaring an incorrect total investment
Including costs that must be excluded, such as land-use costs, compensation, or taxes, in the fee base may result in an estimate that is higher than the applicable amount. The declared value should match the project, building, or item within the appraisal scope.
Understating the investment value within the appraisal scope can also create inconsistencies with the application. The investor or owner is responsible for the accuracy of the total investment used to calculate the fee.
9.2. Confusing “approval” with “appraisal”
“Fire safety design approval” remains common in everyday usage and in documents issued under earlier regulations. Since July 1, 2025, the current legal framework uses the term “fire safety design appraisal” for the corresponding procedure.
When reviewing regulations or preparing an application, businesses should check the regulations currently in force and use the terminology for the current procedure. This helps prevent the use of an outdated fee schedule, procedure, or document.
9.3. Failing to check fee reduction policies
The amount payable may change when a fee reduction policy is in effect. If a business calculates only the base amount under Circular 70/2025/TT-BTC, it may overestimate the fee actually payable.
When calculating the fee, check the payment date and eligibility for any benefit. If more than one policy under Circular 117/2026/TT-BTC applies, use the highest reduction rather than combining the reductions.
9.4. Submitting to the wrong authority
Identifying the wrong appraisal authority may result in the application being transferred to the competent authority or some procedures having to be repeated. Jurisdiction should be checked based on the project or building type and the regulations in force, including the provisions amended by Decree 347/2026/ND-CP.
The appraisal authority also affects the applicable fee arrangements. If a construction-specialist authority appraises fire safety content as part of construction investment procedures, the fee is determined under the corresponding construction appraisal regulations instead of directly applying the fee schedule in Circular 70/2025/TT-BTC.
10. Legal risks of nonpayment or late payment
The immediate consequences of late payment relate to the application status and processing deadlines in the system. Administrative penalties for fire safety violations are determined by the specific violation, not solely by late fee payment.
10.1. The appraisal document may not be issued
For applications handled by the Police, a payment notice may be sent after the appraisal document has been issued. Therefore, late payment does not automatically mean that the Police will refuse to issue the appraisal document. Businesses should track the appraisal result status and payment obligation separately on the Public Service Portal.
10.2. The application is canceled after 30 days
If the applicant has not paid within 30 days of the system sending the notice, the application is automatically canceled. Businesses should monitor their email, text messages, and registered Public Service Portal account so they can respond within the required period.
10.3. Administrative penalties
Fire safety penalties are determined by the specific violation. Late payment of the appraisal fee does not automatically result in a fixed fire safety penalty. Businesses should track the fee payment obligation separately from legal requirements for appraisal, construction, acceptance, and putting the building into operation. If a violation occurs, the form and amount of the penalty are determined under the regulations applicable to that violation.
11. Important considerations for fire safety design review fees
Before budgeting for and paying fire safety design review fees, businesses should check the fee base, applicable policies, and appraisal authority. Key points include:
- Distinguish appraisal fees from other fire safety costs: The government fee is separate from consulting, design, construction, testing, and application preparation services.
- Use the correct fee base: The total investment must match the appraisal scope and exclude costs as required by regulations.
- Check fee limits and reductions: Compare the amount with the minimum and maximum thresholds and any fee reduction policy in effect at the relevant time.
- Pay according to the notice: For applications handled by the Police, payment is made after the system sends the amount due.
- Track the payment deadline: Applications on the Ministry of Public Security Public Service Portal are automatically canceled if payment is not made within 30 days of the notice.
- Apply current regulations: Use Circular 70/2025/TT-BTC and any fee exemption or reduction policies in effect to determine the amount payable.
- Confirm the appraisal authority: The authority conducting the appraisal affects the procedure and fee arrangements applicable to the application.
Fire safety design review fees should be calculated using the correct appraisal scope, total investment fee base, and fee policies in effect. For office design and build projects, businesses should check these factors while preparing the application to budget appropriately and reduce the likelihood of adjustments during the fire safety procedure.
11. Frequently asked questions (FAQ)
11.1. When are fire safety design review fees not required?
No fire safety design review fee is required when: (1) the building’s design is adjusted without renovation or a change of use; (2) the building does not fall under Appendix III of Decree 105/2025/ND-CP because it is below the thresholds for number of floors, area, or volume; (3) a construction-specialist authority appraises the fire safety content and the construction appraisal fee has already been paid; or (4) a transport vehicle is appraised by a vehicle registration authority, in which case an inspection fee is paid instead of a fire safety design appraisal fee.
11.2. Can fire safety design appraisal fee reductions be combined?
No. Fire safety design appraisal fee reductions cannot be combined. Under Circular 64/2025/TT-BTC, the 50% reduction applies generally from July 1, 2025, to December 31, 2026, but cannot be combined with other reductions. The investor may receive only one reduction and cannot double or combine multiple benefits.
11.3. Can a business pay the fire safety design appraisal fee directly?
Yes. A business can pay the fire safety design appraisal fee directly. The fee payer is the investor (the business), which can pay online through the Ministry of Public Security Public Service Portal by QR code, bank transfer, or e-wallet. No intermediary is required; the business only needs to register an account, look up the application code, and follow the system instructions.
11.4. Does an adjusted design require another fire safety design appraisal fee?
An adjusted design requires another fire safety design appraisal fee only when the entire approved design scheme changes, including its scale, function, use, or fire safety solutions. If only part of an item or fire safety system is adjusted, the Police may consider issuing a supplemental document without charging a fee. From July 1, 2025, to December 31, 2026, the appraisal fee for an adjusted design is reduced by 50%.
11.5. What happens if the fee is not paid by the deadline?
If the fire safety design appraisal fee is not paid by the deadline (within 30 days of receiving the notice), the application is automatically canceled in the system. The investor must submit a new application from the beginning, which takes additional time and may incur a new fee. Paying as soon as the notice arrives helps prevent additional costs and project delays.